12. You are finalizing your capital budgeting analysis on whether to proceed with a new plant and are almost ready to present it to your boss. One of your particularly lazy and dim-witted team members comes sauntering in at the last minute and starts arguing about some of the details. He states that the analysis should not have included the land that the plant will be built-on because it's already bought and paid-for. He further argues that you've neglected to include the cost of the exploratory engineering design completed last year when this project was first conceived. Explain exactly what is wrong with his arguments. [6 pts]