Use the following STRIP table to figure the NPV a project that has these cash flows:

STRIP Table:

Maturity of STRIP

Bid Price

Ask Price

August 2019

96.01

96.02

February 2020

92.22

92.25

August 2020

88.13

88.16

February 2021

84.65

84.75

Cash flows:

Today

February 2020

February 2021

-$10,000

+$70,000

+$10,000

Show Answer