23.10
10.The risk free rate is 4%. The return on the market is expected
to be 14%. You must choose between the following two projects
that require the same piece of land and last only one year.
Project A |
Project B |
|
Initial Outlay | -500 |
-700 |
Expected Cash flow next year | +800 |
+900 |
Beta (b ) | 1.1 |
0.7 |