24

24.1
Consider the following two projects:
   

  Year 0 Year 1 Year 2 Year 3
A -5000 2500 2500 2500
B -2000 1000 -500 3000

 

  1. Assume that your opportunity cost of capital is 12%. What are the NPVs of projects A & B and which would you take if you could only take one? Explain. (DO NOT just say, 'It has the higher NPV.' Tell me what that means and why it is relevant). (2 pts)

Show Answer